Learning through Volcano's unique natural and cultural resources to become creative global citizens.
Old Volcano Road Makai Campus

.jpg)
​​​
Volcano School is building a campus for its secondary 6-12 grade and pre-Kindergarten programs.
​
With the lease on Old Volcano Road mauka ending May of 2028, school leadership has been working to identify a viable solution.
​
W. H. Shipman, Ltd. (WHSL) has agreed to partner with the Volcano School to develop facilities on Old Volcano Road between Nahelelani Street and Aliʻi Anela Street.
​
Friends of The Volcano School of Arts & Sciences has purchased a 10 acre parcel adjacent to the WHSL site, which will eventually provide additional facilities to support the educational program.
​
​Plans for the OVR Makai Campus include Middle School, High School, and PreKindergarten pod spaces; a central piko courtyard, an administrative building, cafeteria, labs, shops, and outdoor courts.
​
The initial phase will focus on facilities for high school and preKindergarten to accommodate current enrollment. Subsequent phases will provide facilities for middle school along with additional labs and shops.
​
The campus site plan is set back on the property to provide space for community access facilities such as for performing arts, hula, theater, sports, commercial kitchen, and community events. ​
Milestones
-
Right of Entry executed with WHSL, September 16, 2024
-
Envi ronmental Assessment initiated, October 25, 2024
-
Conceptual Site Plan completed, January 8, 2025
​Estimated Timeline
-
License agreement executed with WHSL, March 2025
-
Special Use Permit Application, March 2025
-
Planning Commission acceptance, July 2025
-
Master Site Plan approval, October 2025
-
Phase I permit set completed, October 2025
-
Grubbing & Grading for Phase I completed, January 2026
-
Building permit Phase I, April 2026
-
Phase I completed, June 2027
​​​​​​
Get Involved
We invite you to come be a part of this exciting project and join the Friends of VSAS, the non-profit board tasked with overseeing and managing development of the new campus.
​
Questions
To inquire about joining the Friends of VSAS board or for more information on the Old Volcano Road Makai Campus, contact friends@volcanoschool.net.
​